A full list of the road safety improvement works delivered during financial year 2013/14 can be seen below. 

Improvements Delivered – Tore Roundabout

IssueSchemeDelivery DateValue

Vulnerable Road User Study

Improved crossing facilities for pedestrians and cyclistsDecember 2015£120,000

 

 

Improvements Delivered – Ord of Caithness

IssueSchemeDelivery DateValue

Identified barrier issue
at bend / vehicle left carriageway

Improved barrier provision to
cover full bend
March 2014£37,000

 

Improvements Delivered – Portgower

IssueSchemeDelivery DateValue (£)
Drainage

Replacement of existing bridge and road re-alignment

April 2014

£800,000

 

Improvements Delivered – Tain North

IssueSchemeDelivery DateValue (£)

Historical Accident Site

High Friction surfacing and lining

August 2015

£20,000